Four months in and we have real, visible progress on the Children’s Centre building. Let me walk you through it.
The 5 levels of the project
- Landscape โ โ Done
- Foundation โ โ Done
- Walls โ ๐จ In progress
- Roofing and plastering โ Upcoming
- Doors and windows โ Final stage
The Covid-19 pandemic has slowed us down โ donations are tight for everyone right now โ but we are still building. Every week there’s more to show.
What this building will do
- Accommodate 150 children who cannot afford private schools
- Provide classrooms, a kitchen, toilets, and a store room
- Save us the rent we’ve been paying for 9 years โ freeing up that money to feed the children
Building dimensions
Main room: 10m ร 12m. Sub-room: 4m ร 6m.
Budget for the next level (walls)
- 700 cement bricks ร MWK 220 = MWK 154,000
- Plus mortar, reinforcement, and labour
๐ Help us reach the roof. Give towards the walls.